Cleveland Avenue Isn't Closed. It's Being Rebuilt One Block at a Time.

October 1, 2026

Which businesses on Wellington's Main Street are actually open this week? It's a fair question if you drive past the orange cones and construction fencing along Cleveland Avenue and assume the whole corridor is a lost cause until further notice. It isn't. The town has been rebuilding this street in careful sequence since spring, and once you understand the order of operations, you know exactly which block to expect trouble on and which ones are business as usual.

The project is the Cleveland Avenue Construction Project, a rebuild of Wellington's historic Main Street funded by $4,476,822 in grants from the Colorado Department of Transportation. Preliminary work began in late May, with crews locating waterlines on 1st, 3rd, 5th and 6th streets before any pavement came up. Phase 1 started May 28 along 5th Street between Cleveland and Kennedy avenues, and work moved onto Cleveland Avenue itself starting as early as June 3, beginning on the south side of the road. As of this month, the town's project page still lists Cleveland Avenue work as active, with completion expected late fall or early winter.

That timeline matters less than the order it followed, because the order is the reason downtown hasn't gone dark for six months straight.

The Town Started With What You Don't See

Before a single storefront lost street parking, Wellington spent March and April rebuilding the alleys behind Cleveland Avenue, one side at a time. The alley between 1st and 2nd streets got a new concrete drain pan and regrading on its north side first, then its south side. The alley between 2nd and 3rd streets followed, with the west side closed from March 30 through April 6 and the east side closed April 13 through 20. None of that touched the sidewalks or parking spots customers actually use to reach a shop door.

That sequencing wasn't an accident. The alley work existed to handle drainage and prep the ground behind the businesses so that when construction finally reached the street itself, crews weren't discovering surprises mid-block. It bought the corridor several extra weeks of normal front-door access while the harder infrastructure work happened out of sight.

The same logic carried into the street phase. Rather than closing Cleveland Avenue end to end, the town split the corridor into phases and, within each phase, by side of the road. Fifth Street took the brunt of it first because it carries less foot traffic to storefronts than Cleveland Avenue proper. Only after that work was underway did crews turn to the highway-facing block itself, and even there the town has kept Cleveland Avenue open to local traffic through most of the project, warning of short-term closures rather than a blanket shutdown.

What $4.4 Million Is Actually Buying

The grant money covers new storm drainage, ADA-compliant ramps and ped crossings, better lighting, and a reconfigured parking layout. Wellington public works director Bob Gowling described the funding structure at a town meeting covered by CitizenPortal.ai:

"With that $4,400,000 in grant money, we've added quite a bit of town money."

The finished design is expected to deliver roughly 90 parking spaces and eight ADA-accessible spaces along the corridor, a number the town settled on specifically because on-street parking has been one of the biggest disruptions during construction. Town staff also split the project into two tiers on purpose: essential civil work like drainage and ramps got funded first, with benches, decorative lighting and landscaping treated as add-ons that can wait if bids come in high. That's a practical hedge, not a downgrade. It means the corridor's safety and access upgrades aren't at risk even if the prettier finishing touches slip to a later date.

What's Actually Open Right Now

If you're planning an errand run or a coffee stop downtown, the businesses that predate this project are still operating through it. Owl Canyon Coffee, at 3745 Cleveland Avenue in a building that dates to 1903, is still pouring espresso and serving breakfast burritos out of Wellington's only independent coffee shop. Directly across the street, Old Colorado Brewing Company keeps its downtown taproom pouring craft beer and wine, and Soul Squared Brewing runs its Wellington taproom at 3740 Cleveland Avenue, the local outpost of a farm-based brewery that brews offsite.

A few blocks over, Wellington Grill on 2nd Street, the T-Bar Inn on West Cleveland Avenue, and Pizza Palace on Cleveland Avenue have kept regular hours through the alley work and the early street phases. None of these sit in the segments that saw the heaviest early disruption, which is part of why the corridor doesn't feel abandoned even mid-project.

The one business that opened into the middle of all this is Fernandito's Mexican Grill, which brought its first-ever Colorado location to 6th Street near the Wellington I-25 exit in early 2026, taking over the spot that used to be Taco John's. It's a small chain out of Laramie, Wyoming, with one other location, and choosing to expand into Wellington the same year the town tore up its Main Street says something about how contained the disruption has actually been. A business doesn't plant its first Colorado flag in a town it expects to be a construction zone for a year straight.

Even the Fourth of July Had to Route Around It

The clearest evidence of how seriously the town is managing this project around its calendar showed up on Independence Day. Wellington's Fourth of July celebration is normally a downtown event, but this year the parade moved entirely off Cleveland Avenue and onto the streets surrounding Wellington Middle/High School, with the town stating plainly that downtown would be under construction through the summer. Shuttles ran between the school, Centennial Park and Wellington Community Park to keep the day's usual stops connected. The town didn't cancel or shrink the event. It rerouted around the one corridor it knew wouldn't be usable that week, which tells you the same thing the alley sequencing does: this is a project being actively managed around the businesses and traditions that depend on the street, not one running independent of them.

Town staff, the Wellington Main Street Program and the Wellington Area Chamber of Commerce have also convened a Cleveland Construction Committee specifically to help businesses through the construction window, working on parking alternatives, signage and event coordination so foot traffic doesn't just evaporate while the street is torn up.

What This Looks Like Into Winter

Work on Cleveland Avenue itself is expected to run into late fall or early winter, which means the next several weeks are likely the last stretch of active construction before the corridor settles into its finished layout. If you've been avoiding downtown because you assumed the whole street was shut, this is the point to reconsider. The businesses that have carried the corridor through spring and summer are still there, the sequencing that's protected them so far isn't changing, and the payoff on the other side is a Main Street with better lighting, more accessible ramps and a parking layout built with the input of the people running businesses on it.

If you want to track exactly what's happening on which block before you plan a trip downtown, the town posts phase updates directly on its Cleveland Avenue Construction Project page, and you can find more on daily life in town through our Wellington neighborhood guide.